Study PMI-SP Sequencing and Estimating: key concepts, common traps, and exam decision cues.
Sequencing, estimating, and resource logic are the core of schedule realism. PMI-SP expects you to define dependencies, durations, and resource assumptions in a way that produces a credible model instead of a politically attractive one.
The exam is looking for sound schedule logic. Relationships should reflect real work, calendars should be realistic, and duration estimates should be grounded in method and available data. Resource logic also matters because unrealistic loading can make the schedule appear feasible when it is not.
Strong answers recognize that sequencing and estimating are linked. A weak dependency structure can make a good estimate meaningless, and a weak estimate can distort even a technically sound network.
Stronger answers:
Weaker answers:
The sponsor wants a key milestone earlier than the current schedule supports, and the team suggests adding hard date constraints instead of reworking logic and estimates. What is the strongest PMI-SP response?
A. Add the constraints because milestone dates matter more than network logic B. Reassess logic, calendars, and estimating assumptions before forcing the milestone with constraints C. Keep the constraints temporary and hope they can be removed later D. Leave the milestone unchanged and stop further discussion
Best answer: B
PMI-SP strongly favors schedule truth over cosmetic compliance. B protects network integrity and realistic estimating before resorting to forceful constraints. A and C make the schedule look better without making it truer. D avoids analysis.